Calculates the number of days that you can delay a task without impacting the project finish date.
Syntax
TOTALFLOAT(Value)
- Value—The row where you would calculate the TotalFloat function
Sample usage
=TOTALFLOAT([Primary Column]@row)
Examples
=TOTALFLOAT([Task Name]@row)
This formula function returns the TotalFloat for this given task at any specified row.
You may see the #INVALID COLUMN VALUE error if you haven't enabled dependencies.
You can reference any column as the Value, as long as the row reference is the correct row to evaluate.